Cyma Builders Completes Fast – Tracked Laboratory Renovation for DPT Laboratories in Lakewood, NJ
Cyma Builders was engaged by DPT Laboratories to relocate a critical laboratory function from a leased building to a newly purchased site. The 3,000 SF fit-out was budget constrained and required close coordination between construction and design teams to ensure a workable design was established and maintained. Eight weeks was allotted for construction with on-time delivery necessary to avoid punitive lease clauses in the existing building. Project scope consisted of HVAC, lab gas and electrical distribution to accommodate the new program. New casework and fume hoods were installed, along with a new epoxy flooring system. Client occupancy and equipment validation commenced immediately upon substantial completion of construction, and allowed the leased space to be successfully vacate by the 3/22 deadline.